Description: Purchase 3 hydrogen electric buses & 5 Gal buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Bakersfield
Zip Code 93301
 
Senate District
14
Assembly District 34
Congressional District 23
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      100  
Increased Ridership      45  
Reduced Emissions  40    100  
Reduced Operating/Maintenance Cost      90  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DENISE SAILES (661) 861-6322   DSAILES@GETBUS.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$0 $1,458 $1,458
PTMISEA-99314
$0 $159 $159
Non-bond Funding
 
Total**** $0 $1,617 $1,617

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$0 $1,617 $1,617 $1,617 $1,617 $0
 
Total* $0 $1,617 $1,617 $1,617 $1,617 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
11/01/2019 

02/01/2020 
01/20/2022 

01/20/2022 
08/01/2020 

11/01/2021 
100   

 


Begin Closeout Phase

End Closeout Phase
04/01/2020 

04/30/2021 
01/20/2022 

01/20/2022 
11/01/2021 

12/31/2021 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 100
Increased Ridership 45
Reduced Emissions 40 100
Reduced Operating/Maintenance Cost 90

Bond Funding Cost
Adopted:
$0
Current Approved:
$1,616,801
Actual Expenditures:
$1,616,801

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31