Caltrans Logo

Match for CMAQ Bus Purchase

Description: Match for federal CMAQ grant to purchase (4) 40', 41 passenger, 2 wheelchair CNG El Dorado National Buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Bakersfield
Zip Code 93301
 
Senate District
18
Assembly District 32
Congressional District 20, 22
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Reduced Emissions  10    10  
Reduced Operating/Maintenance Cost  10    10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DENISE HAYNES (661) 862-5078   HANYNESD@CO.KERN.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$44 $0 $44
PTMISEA-99314
$2 $0 $2
Non-bond Funding
State/Federal*
$1,432 $0 $1,432
Local**
$191 $0 $191
 
Total**** $1,669 $0 $1,669

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,669 $0 $1,669 $1,669 $1,669 $0
 
Total* $1,669 $0 $1,669 $1,669 $1,669 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/01/2015 

12/31/2015 
 

 
09/01/2014 

06/30/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2016 

07/31/2016 
 

 
06/30/2015 

07/28/2015 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Emissions 10 10
Reduced Operating/Maintenance Cost 10 10

Bond Funding Cost
Adopted:
$45,592
Current Approved:
$45,592
Actual Expenditures:
$45,592

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31