Transit Connect Vehicles

Description: Purchase 2 transit connect vehicles, 15 passengers, 2015 Ford Transit Wagon XLT, long wheel base, medium roof height, 3 7L V-6 engine with CNG/LPG

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Mcfarland
Zip Code 93250
 
Senate District
14
Assembly District 32
Congressional District 21
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  5    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JOHN WOONER (661) 792-3091   JWOONER@MCFARLANDCITY.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$80 $-9 $71
PTMISEA-99314
$2 $0 $2
Non-bond Funding
 
Total**** $81 $-9 $72

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$81 $-9 $72 $72 $72 $0
 
Total* $81 $-9 $72 $72 $72 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/01/2015 

04/30/2015 
 

 
04/01/2015 

04/30/2015 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/01/2015 

07/31/2015 
 

 
05/01/2015 

07/31/2015 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2015 

09/30/2015 
06/08/2016 

06/08/2016 
08/07/2015 

10/01/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
11/01/2015 

12/31/2015 
06/08/2016 

06/08/2016 
01/01/2016 

01/31/2016 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 5 5

Bond Funding Cost
Adopted:
$81,389
Current Approved:
$72,236
Actual Expenditures:
$72,236

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31