Caltrans Logo

Transit Shelter Maintenance

Description: Transit shelter grafitti removal, stucco repair, pressure washing and painting

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Shafter
Zip Code 93263
 
Senate District
30
Assembly District 16
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  1      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JAMES ZERVIS (661) 746-5001   JZERVIS@SHAFTER.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$4 $0 $4
PTMISEA-99314
$0 $0 $0
Non-bond Funding
Local**
$0 $8 $8
 
Total**** $4 $8 $12

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$4 $8 $12 $12 $12 $0
 
Total* $4 $8 $12 $12 $12 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
03/01/2015 

04/01/2015 
 

 
03/01/2015 

04/01/2015 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2015 

04/15/2015 
 

 
04/01/2015 

04/15/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/01/2015 

06/01/2015 
 

 
05/01/2015 

06/01/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2015 

06/30/2015 
07/16/2019 

07/16/2019 
06/01/2015 

06/30/2015 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 1

Bond Funding Cost
Adopted:
$3,767
Current Approved:
$3,767
Actual Expenditures:
$3,767

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31