Caltrans Logo

Purchase 2 Transit Buses

Description: Purchase 2 Chevy Glaval 23', Type B, V8, 14 passenger & 2 wheelchair capacity, Gasoline Buses,

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Taft
Zip Code 93268
 
Senate District
32
Assembly District 18
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  20    20  
Reduced Operating/Maintenance Cost  20    20  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
TERESA BINKLEY (661) 763-1350   TBINKLEY@CITYOFTAFT.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$57 $0 $57
PTMISEA-99314
$35 $70 $105
Non-bond Funding
 
Total**** $91 $70 $161

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$91 $70 $161 $161 $161 $0
 
Total* $91 $70 $161 $161 $161 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2015 

12/31/2015 
03/06/2016 

03/06/2016 
05/19/2015 

07/31/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
02/15/2016 

03/15/2016 
03/06/2016 

03/06/2016 
12/31/2015 

01/31/2016 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 20 20
Reduced Operating/Maintenance Cost 20 20

Bond Funding Cost
Adopted:
$91,343
Current Approved:
$161,343
Actual Expenditures:
$161,343

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31