Purchase (2) 14 Passenger Buses

Description: Purchase (2) 23 ft, 14 passenger, buses (1 CNG & 1 Gas fueled) for Dial-a-Ride to include wheelchair lift, space for 2 wheelchairs replacement buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Wasco
Zip Code 93280
 
Senate District
16
Assembly District 32
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  15      
Increased Ridership      19  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
BOB WREN (661) 758-7219   BOWREN@CI.WASCO.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99313
$169 $4 $172
PTMISEA-99314
$4 $0 $4
Non-bond Funding
 
Total**** $172 $4 $177

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$172 $4 $177 $177 $177 $0
 
Total* $172 $4 $177 $177 $177 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/04/2015 

06/01/2015 
 

 
05/04/2015 

06/01/2015 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2015 

08/17/2015 
08/13/2015 

05/20/2019 
07/10/2015 

03/22/2019 
100   

 


Begin Closeout Phase

End Closeout Phase
09/01/2015 

10/05/2015 
05/20/2019 

05/20/2019 
03/22/2019 

04/19/2019 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 15
Increased Ridership 19

Bond Funding Cost
Adopted:
$172,396
Current Approved:
$176,090
Actual Expenditures:
$176,090

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31