New Bus Purchase

Description: Purchase 3 new 35' CNG buses for route expansions. Seating capacity of 35, low floor design, with ADA equipment

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kings
City Hanford
Zip Code 93230
 
Senate District
16
Assembly District 30
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  5      
Reduced Emissions  10    10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ANGIE DOW (559) 852-2691   ANGIE.DOW@CO.KINGS.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $27 $27
PTMISEA-99313
$1,162 $16 $1,178
PTMISEA-99314
$316 $0 $316
Non-bond Funding
State/Federal*
$0 $1,060 $1,060
 
Total**** $1,478 $1,103 $2,581

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,478 $1,103 $2,581 $2,581 $2,581 $0
 
Total* $1,478 $1,103 $2,581 $2,581 $2,581 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2015 

04/15/2015 
08/21/2015 

08/21/2015 
06/01/2015 

08/30/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/30/2015 

05/30/2015 
08/21/2015 

08/21/2015 
09/01/2015 

12/01/2015 
50   

 


Begin Closeout Phase

End Closeout Phase
06/01/2016 

06/30/2016 
03/10/2016 

03/10/2016 
08/20/2015 

08/30/2016 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 5
Reduced Emissions 10 10

Bond Funding Cost
Adopted:
$1,477,904
Current Approved:
$2,581,156
Actual Expenditures:
$2,581,156

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31