ZEB Chargers and Infrastructure Costs

Description: PTMISEA interest-only project. ZEB charging infrastructure to support fleet and CARB's 2040 goal.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Norwalk
Zip Code 90650
 
Senate District
32
Assembly District 57
Congressional District 38
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  5    20  
Reduced Emissions  15      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MELANIE PAZ (562) 929-5660   MPAZ@NORWALKCA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $54 $54
Non-bond Funding
State/Federal*
$0 $107 $107
Local**
$0 $30 $30
 
Total**** $0 $191 $191

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $107 $107 $0 $0 $107
Construction
$0 $84 $84 $191 $191 $-107
 
Total* $0 $191 $191 $191 $191 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2022 

06/30/2023 
02/15/2023 

04/26/2023 
08/01/2022 

08/30/2022 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2023 

09/01/2023 
04/26/2023 

04/26/2023 
05/01/2023 

05/30/2023 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5 20
Reduced Emissions 15

Bond Funding Cost
Adopted:
$0
Current Approved:
$0
Actual Expenditures:
$0

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31