Purchase & Improvements of Operations and Maintenance Facility |
Description: Purchase land to construct a maintenance facility for Merced
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Merced |
City | Merced |
Zip Code | 95340 |
Senate District |
12 |
Assembly District | 17 |
Congressional District | 18 |
Caltrans District |
10 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Operating/Maintenance Cost | 20 | 10 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
DARIANA LUA | (209) 723-3100 | DLUA@MERCEDTHEBUS.COM |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $37 | $37 | ||||
PTMISEA-99313 |
$2,611 | $0 | $2,611 | ||||
PTMISEA-99314 |
$115 | $0 | $115 | ||||
Non-bond Funding | |||||||
Local** |
$0 | $4,919 | $4,919 | ||||
Total**** | $2,726 | $4,955 | $7,681 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$160 | $0 | $160 | $160 | $160 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$2,566 | $4,955 | $7,521 | $7,521 | $7,521 | $0 | |
Total* | $2,726 | $4,955 | $7,681 | $7,681 | $7,681 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
10/01/2015 11/30/2015 |
03/15/2016 03/15/2016 |
05/02/2016 09/02/2016 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
05/01/2016 12/30/2016 |
09/05/2017 07/26/2018 |
08/01/2017 11/15/2018 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
01/15/2017 02/01/2017 |
08/22/2019 08/22/2019 |
10/01/2019 10/31/2019 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Operating/Maintenance Cost | 20 | 10 |
Bond Funding Cost | |
---|---|
Adopted: |
$2,726,163 |
Current Approved: |
$2,726,163 |
Actual Expenditures: |
$2,726,163 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31