Purchase & Improvements of Operations and Maintenance Facility

Description: Purchase land to construct a maintenance facility for Merced

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Merced
City Merced
Zip Code 95340
 
Senate District
12
Assembly District 17
Congressional District 18
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  20    10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DARIANA LUA (209) 723-3100   DLUA@MERCEDTHEBUS.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $37 $37
PTMISEA-99313
$2,611 $0 $2,611
PTMISEA-99314
$115 $0 $115
Non-bond Funding
Local**
$0 $4,919 $4,919
 
Total**** $2,726 $4,955 $7,681

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$160 $0 $160 $160 $160 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,566 $4,955 $7,521 $7,521 $7,521 $0
 
Total* $2,726 $4,955 $7,681 $7,681 $7,681 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/01/2015 

11/30/2015 
03/15/2016 

03/15/2016 
05/02/2016 

09/02/2016 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/01/2016 

12/30/2016 
09/05/2017 

07/26/2018 
08/01/2017 

11/15/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
01/15/2017 

02/01/2017 
08/22/2019 

08/22/2019 
10/01/2019 

10/31/2019 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 20 10

Bond Funding Cost
Adopted:
$2,726,163
Current Approved:
$2,726,163
Actual Expenditures:
$2,726,163

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31