Town of Loomis Community Transit Enhancement Multi-modal Transit Station EV Charge Station

Description: Provide community transit enhancement at the Town of Loomis Multi-Modal Transit Station by dedicating two park-n-ride stalls at the Multi-Modal transit Station for installation of an EV charge station

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Placer
City Auburn
Zip Code 95603
 
Senate District
04
Assembly District 01
Congressional District
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Reduced Emissions  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DAVID MELKO (530) 823-4090   DMELKO@PCTPA.NET
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$51 $-39 $13
Non-bond Funding
 
Total**** $51 $-39 $13

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$51 $-39 $13 $13 $13 $0
 
Total* $51 $-39 $13 $13 $13 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2015 

01/30/2015 
 

 
01/01/2015 

01/30/2015 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/01/2015 

02/28/2015 
 

 
02/01/2015 

02/28/2015 
 

 


Begin Right of Way Phase

End Right of Way Phase
03/01/2015 

04/01/2015 
 

 
03/01/2015 

04/01/2015 
 

 


Begin Construction Phase

End Construction Phase
07/01/2015 

08/01/2015 
08/29/2016 

08/29/2016 
03/01/2016 

05/09/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
09/01/2015 

10/01/2015 
08/29/2016 

08/29/2016 
06/01/2016 

06/30/2016 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Emissions 1 1

Bond Funding Cost
Adopted:
$51,366
Current Approved:
$12,643
Actual Expenditures:
$12,643

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31