Caltrans Logo

Placer County Bus Replacements

Description: Replace 7 buses, 5 (five) 18-passenger Dial-a-Ride and 2 (two) 35'-40' fixed route for Placer County Transit Services.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Placer
City Auburn
Zip Code 95603
 
Senate District
04
Assembly District 01
Congressional District
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10    20  
Reduced Emissions      30  
Reduced Operating/Maintenance Cost      20  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
WILL GARNER (530) 745-7582   WGARNER@PLACER.CA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $30 $30
PTMISEA-99313
$796 $0 $796
PTMISEA-99314
$192 $0 $192
Non-bond Funding
State/Federal*
$0 $87 $87
Local**
$0 $56 $56
 
Total**** $988 $173 $1,162

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$988 $173 $1,162 $1,162 $1,162 $0
 
Total* $988 $173 $1,162 $1,162 $1,162 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2015 

12/01/2016 
09/28/2018 

09/28/2018 
11/30/2015 

10/31/2017 
100   

 


Begin Closeout Phase

End Closeout Phase
12/01/2016 

01/01/2017 
09/28/2018 

09/28/2018 
10/31/2017 

07/31/2018 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10 20
Reduced Emissions 30
Reduced Operating/Maintenance Cost 20

Bond Funding Cost
Adopted:
$988,200
Current Approved:
$988,200
Actual Expenditures:
$988,200

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31