Caltrans Logo

Ceres Bus Shelter & Bus Stop Improvements

Description: Install and improve Ceres Transit bus stops

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Stanislaus
City Modesto
Zip Code 95354
 
Senate District
12, 14
Assembly District 25, 26
Congressional District 18
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  3    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
REGINA VALENTINE (209) 525-4644   RVALENTINE@STANCOG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $12 $12
PTMISEA-99313
$236 $0 $236
Non-bond Funding
 
Total**** $236 $12 $248

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$2 $0 $2 $2 $2 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$234 $12 $246 $246 $246 $0
 
Total* $236 $12 $248 $248 $248 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2015 

08/31/2015 
 

02/26/2016 
07/01/2015 

12/31/2016 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2015 

02/28/2016 
02/26/2016 

08/10/2022 
06/01/2017 

08/01/2022 
100   

 


Begin Closeout Phase

End Closeout Phase
04/30/2016 

06/30/2016 
02/14/2022 

08/10/2022 
08/01/2022 

08/10/2022 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 3 5

Bond Funding Cost
Adopted:
$235,500
Current Approved:
$235,500
Actual Expenditures:
$235,500

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31