Procurement of Para Transit Vehicles

Description: Replacing high mileage paratransit vehicles from the fleet to reliable and efficient public transit service in the region

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Stanislaus
City Modesto
Zip Code 95354
 
Senate District
12
Assembly District 25
Congressional District 10
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  5      
Increased Ridership      1  
Reduced Emissions  10      
Reduced Operating/Maintenance Cost  3      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
EUNICE LOVI (209) 525-7500   LOVIE@STANCOUNTY.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $8 $8
PTMISEA-99313
$500 $0 $500
Non-bond Funding
Local**
$275 $0 $275
 
Total**** $775 $8 $783

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$775 $8 $783 $783 $783 $0
 
Total* $775 $8 $783 $783 $783 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/01/2015 

06/30/2015 
02/26/2016 

02/26/2016 
03/01/2016 

07/01/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
09/01/2015 

10/31/2015 
04/05/2018 

04/05/2018 
04/01/2017 

12/01/2017 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5
Increased Ridership 1
Reduced Emissions 10
Reduced Operating/Maintenance Cost 3

Bond Funding Cost
Adopted:
$500,000
Current Approved:
$500,000
Actual Expenditures:
$500,000

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31