Description: Upgrade the design and layout of all county bus stop signage

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Stanislaus
City Modesto
Zip Code 95354
 
Senate District
12
Assembly District 25
Congressional District 10
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10    30  
Increased Ridership      3  
Reduced Operating/Maintenance Cost      10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
EUNICE LOVI (209) 525-7560   LOVIE@STANCOUNTY.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $7 $7
PTMISEA-99313
$130 $0 $130
Non-bond Funding
Local**
$0 $63 $63
 
Total**** $130 $69 $199

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$130 $69 $199 $199 $199 $0
 
Total* $130 $69 $199 $199 $199 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2015 

09/30/2015 
08/22/2019 

08/12/2020 
11/01/2016 

06/01/2020 
100   

 


Begin Closeout Phase

End Closeout Phase
12/31/2015 

01/31/2016 
08/12/2020 

02/19/2020 
03/01/2020 

06/30/2020 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10 30
Increased Ridership 3
Reduced Operating/Maintenance Cost 10

Bond Funding Cost
Adopted:
$129,951
Current Approved:
$129,951
Actual Expenditures:
$129,951

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31