Bus Stop Improvements

Description: Bus Stop Improvements troughout the City of Turlock

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Stanislaus
City Turlock
Zip Code 95380
 
Senate District
25
Assembly District 12
Congressional District 19
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  2    2  
Reduced Operating/Maintenance Cost  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
SCOTT MEDEIROS (209) 668-5520   SMEDEIROS@TURLOCK.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99313
$150 $0 $150
Non-bond Funding
Local**
$0 $63 $63
 
Total**** $150 $64 $214

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$18 $0 $18 $18 $18 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$132 $64 $196 $196 $196 $0
 
Total* $150 $64 $214 $214 $214 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/01/2015 

05/01/2015 
03/23/2017 

03/23/2017 
04/30/2017 

09/01/2017 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/13/2015 

12/08/2015 
03/23/2017 

03/23/2017 
09/01/2017 

01/11/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
12/08/2015 

02/15/2016 
03/23/2017 

03/23/2017 
01/01/2018 

04/01/2018 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 2 2
Reduced Operating/Maintenance Cost 1 1

Bond Funding Cost
Adopted:
$150,000
Current Approved:
$150,000
Actual Expenditures:
$150,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31