(1) CNG Transit Bus for DART

Description: City of Dinuba to purchase medium duty cut-away CNG, 16 passenger, 2 wheelchair bus

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tulare
City Dinuba
Zip Code 93618
 
Senate District
16, 18
Assembly District 34
Congressional District 21
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  13    5  
Increased Ridership      5  
Reduced Operating/Maintenance Cost  13      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ROY RAMIREZ (559) 591-3278   RRAMIREZ@DINUBA.CA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$125 $-8 $117
Non-bond Funding
 
Total**** $125 $-8 $117

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$125 $-8 $117 $117 $117 $0
 
Total* $125 $-8 $117 $117 $117 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2015 

09/30/2015 
 

 
01/01/2015 

09/30/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
10/15/2015 

11/30/2015 
 

 
10/15/2016 

11/30/2016 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 13 5
Increased Ridership 5
Reduced Operating/Maintenance Cost 13

Bond Funding Cost
Adopted:
$124,697
Current Approved:
$116,610
Actual Expenditures:
$116,610

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31