Caltrans Logo

Web Based Fare System for Electronic Fare Boxes

Description: Purchase web based and mobile fare system. Includes a web based & mobile fare & management system enabling riders to purchase and update fare media online using a computer, tablet, and/or smart phone.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tulare
City Porterville
Zip Code 93257
 
Senate District
34
Assembly District 18
Congressional District 21
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  15    10  
Increased Ridership  5    5  
Reduced Emissions  5    2  
Reduced Operating/Maintenance Cost  5    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
RICHARD TREE (559) 782-7448   RTREE@CI.PORTERVILLE.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $5 $5
PTMISEA-99313
$226 $0 $226
PTMISEA-99314
$18 $0 $18
Non-bond Funding
State/Federal*
$0 $479 $479
Local**
$0 $85 $85
 
Total**** $244 $569 $813

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$244 $569 $813 $813 $813 $0
 
Total* $244 $569 $813 $813 $813 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2015 

03/30/2015 
 

08/21/2015 
01/01/2015 

02/01/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/06/2015 

04/17/2015 
10/13/2020 

10/13/2020 
09/30/2015 

12/31/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
10/01/2015 

11/01/2015 
10/13/2020 

10/13/2020 
10/05/2020 

10/08/2020 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 15 10
Increased Ridership 5 5
Reduced Emissions 5 2
Reduced Operating/Maintenance Cost 5 5

Bond Funding Cost
Adopted:
$243,883
Current Approved:
$243,883
Actual Expenditures:
$243,883

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31