Web Based Fare System for Electronic Fare Boxes |
Description: Purchase web based and mobile fare system. Includes a web based & mobile fare & management system enabling riders to purchase and update fare media online using a computer, tablet, and/or smart phone.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Tulare |
City | Porterville |
Zip Code | 93257 |
Senate District |
34 |
Assembly District | 18 |
Congressional District | 21 |
Caltrans District |
06 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 15 | 10 |
Increased Ridership | 5 | 5 |
Reduced Emissions | 5 | 2 |
Reduced Operating/Maintenance Cost | 5 | 5 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
RICHARD TREE | (559) 782-7448 | RTREE@CI.PORTERVILLE.CA.US |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $5 | $5 | ||||
PTMISEA-99313 |
$226 | $0 | $226 | ||||
PTMISEA-99314 |
$18 | $0 | $18 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $479 | $479 | ||||
Local** |
$0 | $85 | $85 | ||||
Total**** | $244 | $569 | $813 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$244 | $569 | $813 | $813 | $813 | $0 | |
Total* | $244 | $569 | $813 | $813 | $813 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2015 03/30/2015 |
08/21/2015 |
01/01/2015 02/01/2015 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
03/06/2015 04/17/2015 |
10/13/2020 10/13/2020 |
09/30/2015 12/31/2018 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
10/01/2015 11/01/2015 |
10/13/2020 10/13/2020 |
10/05/2020 10/08/2020 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 15 | 10 |
Increased Ridership | 5 | 5 |
Reduced Emissions | 5 | 2 |
Reduced Operating/Maintenance Cost | 5 | 5 |
Bond Funding Cost | |
---|---|
Adopted: |
$243,883 |
Current Approved: |
$243,883 |
Actual Expenditures: |
$243,883 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31