Caltrans Logo

Automatic Passenger Counter System

Description: Purchase automatic passenger counter system. Includes installation of infared sensors on doors of 17 buses.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tulare
City Porterville
Zip Code 93257
 
Senate District
34
Assembly District 18
Congressional District 21
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  25    50  
Increased Ridership      1  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
RICHARD TREE (559) 782-7448   RTREE@CI.PORTERVILLE.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $5 $5
PTMISEA-99313
$302 $0 $302
PTMISEA-99314
$23 $0 $23
Non-bond Funding
 
Total**** $325 $5 $330

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$325 $5 $330 $330 $330 $0
 
Total* $325 $5 $330 $330 $330 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/01/2015 

03/01/2015 
 

 
02/01/2015 

03/01/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2015 

09/01/2015 
08/25/2015 

08/25/2015 
07/07/2015 

01/01/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
10/01/2015 

11/01/2015 
08/24/2021 

08/24/2021 
08/01/2020 

08/24/2021 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 25 50
Increased Ridership 1

Bond Funding Cost
Adopted:
$324,695
Current Approved:
$324,695
Actual Expenditures:
$324,695

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31