(8) 35-Passenger Low Floor CNG Buses

Description: Procure eight 35-passenger low-floor transit buses, 10 bus radios, 10 tablet type mobile data terminals, 10 bus security cameras, 10 zonar mobile fleet mgmt tablets.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno
City Fresno
Zip Code 93721
 
Senate District
14, 16
Assembly District 23, 31
Congressional District 16, 21, 22
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  12      
Increased Ridership  10      
Reduced Emissions  20    10  
Reduced Operating/Maintenance Cost  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MOSES STITES (559) 233-6789   MSTITES@FRESNOCOG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $10 $10
PTMISEA-99313
$1,743 $0 $1,743
Non-bond Funding
Local**
$0 $2,003 $2,003
 
Total**** $1,743 $2,012 $3,756

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,743 $2,012 $3,756 $3,724 $3,724 $32
 
Total* $1,743 $2,012 $3,756 $3,724 $3,724 $32

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2015 

12/01/2015 
07/28/2015 

07/28/2015 
08/07/2015 

08/21/2015 
50   

 


Begin Closeout Phase

End Closeout Phase
02/01/2016 

03/01/2016 
03/09/2016 

03/09/2016 
06/01/2016 

07/01/2016 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 12
Increased Ridership 10
Reduced Emissions 20 10
Reduced Operating/Maintenance Cost 10

Bond Funding Cost
Adopted:
$1,743,134
Current Approved:
$3,724,003
Actual Expenditures:
$3,724,003

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31