Passenger Rail Efficiency Upgrades

Description: A series of projects to improve customer experience. It includes improved walkways, bike paths. It also includes many upgrades to technology, passenger comfort and security.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Riverside
Zip Code 92502
 
Senate District
31
Assembly District 66
Congressional District 44
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  5    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
SHELDON PETERSON (951) 787-7928   SPETERSON@RCTC.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $69 $69
PTMISEA-99313
$3,666 $0 $3,666
Non-bond Funding
 
Total**** $3,666 $69 $3,735

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$300 $0 $300 $300 $300 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$3,366 $69 $3,435 $3,435 $3,435 $0
 
Total* $3,666 $69 $3,735 $3,735 $3,735 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2015 

06/01/2015 
 

 
01/01/2015 

06/01/2015 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/01/2015 

09/01/2015 
 

 
08/01/2015 

09/01/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2015 

02/01/2019 
 

08/13/2020 
10/01/2015 

06/30/2020 
100   

 


Begin Closeout Phase

End Closeout Phase
04/01/2019 

06/30/2019 
08/13/2020 

08/13/2020 
06/30/2020 

08/14/2020 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 5 5

Bond Funding Cost
Adopted:
$3,665,733
Current Approved:
$3,665,733
Actual Expenditures:
$3,665,733

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31