Rolling Stock Procurement & Security Cameras

Description: Purchasing two CNG buses - 32.5 feet, 24 passenger capacity plus 2 wheelchairs - to be used for fixed route service.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Beaumont
Zip Code 92223
 
Senate District
23
Assembly District 42
Congressional District 36
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  20      
Increased Ridership  20    40  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ELIZABETH GIBBS-URTIAGA (951) 769-8521   ELIZABETHU@BEAUMONTCARES.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99313
$238 $0 $238
PTMISEA-99314
$10 $0 $10
Non-bond Funding
 
Total**** $248 $1 $249

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$248 $1 $249 $249 $249 $0
 
Total* $248 $1 $249 $249 $249 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2015 

08/01/2015 
03/06/2016 

03/06/2016 
02/01/2016 

03/22/2016 
90   

 


Begin Closeout Phase

End Closeout Phase
09/01/2015 

12/31/2015 
09/07/2016 

09/07/2016 
09/01/2016 

10/01/2016 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 20
Increased Ridership 20 40

Bond Funding Cost
Adopted:
$247,659
Current Approved:
$247,659
Actual Expenditures:
$247,659

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31