SBMTD Smartcard System

Description: SBMTD will introduce "contactless" technology to its fare collection system. This allows faster boarding, improves data collection, and allows integration with other agencies.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
Santa Barbara
City Santa Barbara
Zip Code 93101
 
Senate District
19
Assembly District 35
Congressional District
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  5    5  
Increased Ridership  5      
Reduced Operating/Maintenance Cost      1  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JERRY ESTRADA (805) 963-3364   JESTRADA@SBMTD.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $2 $2
PTMISEA-99313
$500 $0 $500
PTMISEA-99314
$500 $0 $500
Non-bond Funding
State/Federal*
$0 $121 $121
Local**
$0 $587 $587
 
Total**** $1,000 $710 $1,710

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $14 $14 $-14
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,000 $710 $1,710 $1,695 $1,695 $14
 
Total* $1,000 $710 $1,710 $1,710 $1,710 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/15/2015 

12/15/2016 
08/17/2016 

03/14/2017 
06/01/2016 

01/31/2017 
100   

 


Begin Closeout Phase

End Closeout Phase
01/15/2017 

03/15/2017 
08/30/2017 

08/30/2017 
12/31/2017 

02/28/2018 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5 5
Increased Ridership 5
Reduced Operating/Maintenance Cost 1

Bond Funding Cost
Adopted:
$1,000,000
Current Approved:
$1,000,000
Actual Expenditures:
$1,000,000

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31