Facility Improvements and Equipment

Description: Provide facility improvements, upgrades and replacements, shop and other facility equipment to the RABA transit facility.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Shasta
City Redding
Zip Code 96001
 
Senate District
04
Assembly District 02
Congressional District 02
 
Caltrans District
02
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      5  
Increased Ridership  10      
Reduced Emissions  5      
Reduced Operating/Maintenance Cost  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ANGELA UDOVICH (530) 225-4012   AUDOVICH@CI.REDDING.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $264 $264
PTMISEA-99313
$190 $130 $320
PTMISEA-99314
$10 $0 $10
Non-bond Funding
 
Total**** $200 $394 $594

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$200 $394 $594 $594 $594 $0
 
Total* $200 $394 $594 $594 $594 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
05/01/2015 

09/01/2015 
 

 
05/01/2015 

09/01/2015 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/01/2015 

02/01/2016 
 

 
10/01/2015 

02/01/2016 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2015 

06/01/2015 
04/05/2018 

08/16/2021 
06/01/2016 

07/01/2023 
100   

 


Begin Closeout Phase

End Closeout Phase
02/01/2017 

07/01/2017 
03/05/2023 

08/08/2023 
06/01/2023 

07/31/2023 
25   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5
Increased Ridership 10
Reduced Emissions 5
Reduced Operating/Maintenance Cost 5

Bond Funding Cost
Adopted:
$200,000
Current Approved:
$330,000
Actual Expenditures:
$330,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31