Simi Valley Purchase 6 CNG Paratransit |
Description: Replacing 6 paratransit vans.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Ventura |
City | Ventura |
Zip Code | 93003 |
Senate District |
27 |
Assembly District | 38 |
Congressional District | 25 |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 50 | 50 |
Reduced Operating/Maintenance Cost | 50 | 50 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
STEPHANIE YOUNG | (805) 642-1591 | SYOUNG@GOVENTURA.ORG |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $67 | $67 | ||||
PTMISEA-99313 |
$1,250 | $-81 | $1,169 | ||||
Non-bond Funding | |||||||
Total**** | $1,250 | $-15 | $1,235 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,250 | $-15 | $1,235 | $1,235 | $1,235 | $0 | |
Total* | $1,250 | $-15 | $1,235 | $1,235 | $1,235 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
02/01/2016 05/30/2016 |
01/25/2018 01/25/2018 |
08/17/2015 09/22/2016 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
06/01/2016 07/30/2016 |
01/25/2018 01/25/2018 |
10/01/2017 12/31/2017 |
100 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 50 | 50 |
Reduced Operating/Maintenance Cost | 50 | 50 |
Bond Funding Cost | |
---|---|
Adopted: |
$1,250,000 |
Current Approved: |
$1,168,508 |
Actual Expenditures: |
$1,168,508 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31