Replacement & Expansion Vehicles

Description: Bus replacement and expansion vehicles for enhancements to route 200 and 201 serving Antioch, Pittsburg, and Martinez

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Contra Costa
City Antioch
Zip Code 94509
 
Senate District
07
Assembly District 11, 15
Congressional District 07, 10
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  5    8  
Increased Ridership  2      
Reduced Emissions  10    15  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
TOM HARAIS (925) 754-6622   THARAIS@ECCTA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$179 $0 $179
Non-bond Funding
State/Federal*
$428 $-220 $208
 
Total**** $607 $-220 $387

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$607 $-220 $387 $387 $387 $0
 
Total* $607 $-220 $387 $387 $387 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
02/25/2015 

02/26/2015 
08/21/2018 

08/21/2018 
01/17/2016 

05/17/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
10/31/2016 

12/31/2016 
08/21/2018 

08/21/2018 
05/17/2018 

08/31/2018 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5 8
Increased Ridership 2
Reduced Emissions 10 15

Bond Funding Cost
Adopted:
$178,754
Current Approved:
$178,754
Actual Expenditures:
$178,754

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31