40' Clean Diesel Bus Replacement

Description: Purchase 40' Clean Diesel Bus

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sonoma
City Santa Rosa
Zip Code 95404
 
Senate District
02
Assembly District 10
Congressional District 02, 05
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  5      
Increased Ridership  2      
Reduced Emissions  5      
Reduced Operating/Maintenance Cost  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ANITA WINKLER (707) 543-3330   AWINKLER@SRCITY.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $22 $22
PTMISEA-99313
$672 $851 $1,523
Non-bond Funding
State/Federal*
$491 $-144 $347
Local**
$0 $623 $623
 
Total**** $1,163 $1,352 $2,515

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,163 $1,352 $2,515 $2,515 $2,515 $0
 
Total* $1,163 $1,352 $2,515 $2,515 $2,515 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
11/01/2015 

12/31/2015 
08/29/2017 

02/15/2019 
07/18/2017 

11/30/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
10/01/2016 

11/30/2016 
02/15/2019 

02/15/2019 
12/01/2018 

01/31/2019 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5
Increased Ridership 2
Reduced Emissions 5
Reduced Operating/Maintenance Cost 5

Bond Funding Cost
Adopted:
$671,975
Current Approved:
$1,523,138
Actual Expenditures:
$1,523,138

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31