Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
BART Ticket Vending Machines Upgrades (Clipper Dispensing) |
Description: Implement the purchase and installation of retrofit kits to allow BART Ticket Vending machines to dispense Clipper cards
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Various |
City | Oakland |
Zip Code | 94604 |
Senate District |
03, 09 |
Assembly District | 13, 16 |
Congressional District | 13 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 1 | 1 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
GREGG MARRAMA | (510) 464-7678 | GMARRAM@BART.GOV |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $12 | $12 | ||||
PTMISEA-99313 |
$1,174 | $0 | $1,174 | ||||
Non-bond Funding | |||||||
State/Federal* |
$2,200 | $280 | $2,480 | ||||
Local** |
$0 | $907 | $907 | ||||
Total**** | $3,374 | $1,199 | $4,572 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$3,374 | $1,199 | $4,572 | $3,978 | $3,978 | $595 | |
Total* | $3,374 | $1,199 | $4,572 | $3,978 | $3,978 | $595 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
10/01/2015 06/30/2017 |
|
10/01/2015 06/30/2017 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
07/01/2017 01/31/2018 |
09/05/2019 09/05/2019 |
03/31/2020 12/31/2020 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 1 | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$1,173,544 |
Current Approved: |
$1,173,544 |
Actual Expenditures: |
$1,173,544 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31