Yuba Sutter Front Runner Cutaway Bus Purchase

Description: Purchasing 6 low floor gas powered, 12-passenger FrontRunner cutaway buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Yuba
City Marysville
Zip Code 95901
 
Senate District
04
Assembly District 03
Congressional District 01
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  3    3  
Increased Ridership  3    3  
Reduced Operating/Maintenance Cost  3    3  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
KEITH MARTIN (530) 634-6880   KEITH@YUBASUTTERTRANSIT.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $550 $550
Non-bond Funding
 
Total**** $0 $550 $550

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$0 $550 $550 $0 $0 $550
 
Total* $0 $550 $550 $0 $0 $550

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/01/2022 

09/30/2023 
 

08/14/2023 
12/01/2022 

06/30/2023 
100   

 


Begin Closeout Phase

End Closeout Phase
05/31/2023 

06/30/2023 
08/14/2023 

08/14/2023 
07/01/2023 

07/30/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 3 3
Increased Ridership 3 3
Reduced Operating/Maintenance Cost 3 3

Bond Funding Cost
Adopted:
$0
Current Approved:
$550,000
Actual Expenditures:
$550,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31