Purchase of 70 Replacement CNG 40ft Buses

Description: Purchase of 70 Replacement CNG 40ft Buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Riverside
Zip Code 92507
 
Senate District
20, 23, 28, 31, 37
Assembly District 40, 42, 47, 52, 60, 61, 67, 68
Congressional District 31, 35, 36, 41, 42, 46, 49, 50
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  21    18  
Increased Ridership      1  
Reduced Emissions  27    22  
Reduced Operating/Maintenance Cost      9  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
KRISTIN WARSINSKI (951) 565-5136   KWARSINSKI@RIVERSIDETRANSIT.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$1,223 $50 $1,273
PTMISEA-99313
$11,389 $0 $11,389
PTMISEA-99314
$914 $0 $914
Non-bond Funding
 
Total**** $13,526 $50 $13,576

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$13,526 $50 $13,576 $13,576 $13,576 $0
 
Total* $13,526 $50 $13,576 $13,576 $13,576 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/01/2021 

05/01/2023 
 

 
08/01/2021 

05/01/2023 
100   

 


Begin Closeout Phase

End Closeout Phase
05/31/2023 

06/30/2023 
 

 
05/31/2023 

06/30/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 21 18
Increased Ridership 1
Reduced Emissions 27 22
Reduced Operating/Maintenance Cost 9

Bond Funding Cost
Adopted:
$13,525,958
Current Approved:
$12,302,658
Actual Expenditures:
$12,302,658

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31