Caltrans Logo

Bus Turn Out Construction

Description: Construct a bus turn out lane on State Hwy 18 in Big Bear Lake.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City Big Bear Lake
Zip Code 92315
 
Senate District
17
Assembly District 59
Congressional District
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  5    5  
Increased Ridership      5  
Reduced Emissions      5  
Reduced Operating/Maintenance Cost      5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
KATHY HAWKSFORD (909) 963-7200   KHAWKSFORD@MOUNTAINTRANSIT.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $2 $2
PTMISEA-99313
$200 $200 $400
Non-bond Funding
 
Total**** $200 $202 $402

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$200 $202 $402 $402 $402 $0
 
Total* $200 $202 $402 $402 $402 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
03/01/2016 

08/01/2016 
 

 
03/01/2016 

08/01/2016 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2016 

 
 

 
12/01/2016 

 
100   

 


Begin Right of Way Phase

End Right of Way Phase
12/01/2016 

03/01/2017 
 

 
12/01/2016 

03/01/2017 
 

 


Begin Construction Phase

End Construction Phase
03/01/2016 

06/01/2017 
09/08/2021 

09/08/2021 
07/12/2021 

08/31/2021 
100   

 


Begin Closeout Phase

End Closeout Phase
12/01/2017 

12/30/2017 
09/08/2021 

09/08/2021 
09/01/2021 

09/30/2021 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5 5
Increased Ridership 5
Reduced Emissions 5
Reduced Operating/Maintenance Cost 5

Bond Funding Cost
Adopted:
$200,000
Current Approved:
$400,000
Actual Expenditures:
$400,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31