Purchase Replacement Transit Buses

Description: Purchase of 5 - 30ft. replacement buses, 20-24 passenger seating capacity, diesel powered, with 2 w/c positions,

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tehama
City Gerber
Zip Code 96035
 
Senate District
04
Assembly District 03
Congressional District 01
 
Caltrans District
02
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      100  
Increased Ridership  10      
Reduced Operating/Maintenance Cost      5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
BARBARA O'KEEFFE (530) 385-1462   BOKEEFFE@TCPW.CA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $20 $20
PTMISEA-99313
$667 $0 $667
PTMISEA-99314
$0 $0 $0
Non-bond Funding
Local**
$0 $50 $50
 
Total**** $667 $70 $737

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$667 $70 $737 $737 $737 $0
 
Total* $667 $70 $737 $737 $737 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/01/2016 

03/01/2018 
06/06/2017 

02/26/2020 
06/01/2016 

01/01/2020 
100   

 


Begin Closeout Phase

End Closeout Phase
04/01/2018 

05/01/2018 
02/11/2021 

02/11/2021 
07/01/2021 

08/31/2021 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 100
Increased Ridership 10
Reduced Operating/Maintenance Cost 5

Bond Funding Cost
Adopted:
$666,954
Current Approved:
$666,954
Actual Expenditures:
$666,954

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31