Purchase Seven (7) Commuter Buses

Description: Purchase seven (7) new, 45-ft., 57-passenger, clean-diesel, fleet replacement for Yuba-Sutter Transit intercity commuter service.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sutter, Yuba
City Sacramento
Zip Code 95814
 
Senate District
04
Assembly District 02, 03
Congressional District 02
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  15      
Increased Ridership      18  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
AZADEH DOHERTY (916) 340-6279   ADOHERTY@SACOG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$3,331 $0 $3,331
PTMISEA-99314
$58 $0 $58
Non-bond Funding
 
Total**** $3,389 $0 $3,389

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$3,389 $0 $3,389 $3,389 $3,389 $0
 
Total* $3,389 $0 $3,389 $3,389 $3,389 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2016 

01/01/2018 
 

10/04/2018 
09/30/2017 

01/31/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2018 

06/30/2018 
10/04/2018 

10/04/2018 
07/01/2018 

07/31/2018 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 15
Increased Ridership 18

Bond Funding Cost
Adopted:
$3,389,487
Current Approved:
$3,389,487
Actual Expenditures:
$3,389,487

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31