SYVT - Transit Parking Lot Upgrades

Description: Reconstruct the existing deteriorated parking lot to modern standards - new pavement, concrete curbs, stormwater control. The lot will also be redesigned to meet ADA standards.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Barbara
City Solvang
Zip Code 93463
 
Senate District
19
Assembly District 35
Congressional District 24
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10    10  
Increased Ridership  10    2  
Reduced Emissions  2      
Reduced Operating/Maintenance Cost  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MATT VAN DER LINDEN (805) 688-5575   MATTV@CITYOFSOLVANG.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $4 $4
PTMISEA-99313
$142 $0 $142
PTMISEA-99314
$6 $0 $6
Non-bond Funding
 
Total**** $148 $4 $151

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$25 $0 $25 $25 $25 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$123 $4 $126 $126 $126 $0
 
Total* $148 $4 $151 $151 $151 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2017 

06/01/2017 
 

 
01/01/2017 

06/01/2018 
100   

 


Begin Right of Way Phase

End Right of Way Phase
07/01/2017 

08/01/2017 
 

 
07/01/2017 

08/01/2017 
 

 


Begin Construction Phase

End Construction Phase
10/01/2017 

02/01/2018 
 

 
10/01/2018 

12/01/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
03/01/2018 

05/01/2018 
03/25/2019 

10/02/2019 
04/01/2019 

08/01/2019 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10 10
Increased Ridership 10 2
Reduced Emissions 2
Reduced Operating/Maintenance Cost 5

Bond Funding Cost
Adopted:
$147,713
Current Approved:
$147,713
Actual Expenditures:
$147,713

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31