Caltrans Logo

Front Street Park-n-Ride Lot Expansion, Phase 3

Description: Utility relocation activities to construct additional park-n-ride stalls along Front Street to serve the Rocklin Multi-modal Station.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Placer
City Auburn
Zip Code 95603
 
Senate District
01, 04
Assembly District 06
Congressional District 04
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DAVID MELKO (530) 823-4090   DMELKO@PCTPA.NET
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$82 $0 $82
Non-bond Funding
 
Total**** $82 $0 $83

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$82 $0 $83 $83 $83 $0
 
Total* $82 $0 $83 $83 $83 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
03/30/2017 

05/30/2017 
 

 
03/30/2017 

05/30/2017 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/30/2017 

07/30/2017 
 

 
06/30/2017 

07/30/2017 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/30/2017 

09/30/2017 
09/05/2018 

09/05/2018 
12/07/2017 

06/07/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
10/15/2017 

11/15/2017 
09/05/2018 

09/05/2018 
06/15/2018 

07/15/2018 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 1 1

Bond Funding Cost
Adopted:
$82,302
Current Approved:
$82,302
Actual Expenditures:
$82,302

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31