Caltrans Logo

Paratransit Bus Replacement (2)

Description: Purchase one class C paratransit bus

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
San Bernardino
City Hesperia
Zip Code 92345
 
Senate District
21
Assembly District 33
Congressional District 08
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  2    2  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
KEVIN KANE (760) 995-7446   KKANE@VVTA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$140 $0 $140
Non-bond Funding
State/Federal*
$0 $168 $168
 
Total**** $140 $168 $308

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$140 $168 $308 $308 $308 $-0
 
Total* $140 $168 $308 $308 $308 $-0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/15/2017 

07/30/2017 
 

 
08/15/2017 

08/31/2017 
 

 


Begin Closeout Phase

End Closeout Phase
12/31/2017 

02/15/2018 
 

 
02/15/2018 

04/30/2018 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 2 2

Bond Funding Cost
Adopted:
$140,005
Current Approved:
$140,005
Actual Expenditures:
$140,005

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31