Purchase Class H Replacement Buses

Description: Purchase 3 Replacement Paratransit Vehicles - compressed natural gas

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City Hesperia
Zip Code 92345
 
Senate District
21
Assembly District 33
Congressional District 08
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  2    3  
Increased Ridership      1  
Reduced Emissions      1  
Reduced Operating/Maintenance Cost      3  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
NANCIE GOFF (760) 995-3495   NGOFF@VVTA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$14 $22 $36
PTMISEA-99313
$19 $328 $347
PTMISEA-99314
$0 $0 $0
Non-bond Funding
State/Federal*
$263 $956 $1,219
Local**
$87 $409 $495
 
Total**** $382 $1,715 $2,097

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$382 $1,715 $2,097 $2,097 $2,097 $0
 
Total* $382 $1,715 $2,097 $2,097 $2,097 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/01/2020 

08/14/2020 
02/11/2021 

02/11/2021 
08/21/2020 

11/30/2020 
100   

 


Begin Closeout Phase

End Closeout Phase
03/15/2021 

03/31/2021 
08/16/2022 

02/15/2023 
03/31/2023 

06/30/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 2 3
Increased Ridership 1
Reduced Emissions 1
Reduced Operating/Maintenance Cost 3

Bond Funding Cost
Adopted:
$32,644
Current Approved:
$346,672
Actual Expenditures:
$346,672

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31