Cancelled - SLO Multi-Modal Transportation Center |
Description: Purchase the land for a new multi-modal transportation center in downtown San Luis Obispo. This will replace the 35 year old transfer node along Osos St.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
Project Location | |
---|---|
County |
San Luis Obispo |
City | San Luis Obsipo |
Zip Code | 93401 |
Senate District |
17 |
Assembly District | 35 |
Congressional District | 24 |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 5 | |
Reduced Operating/Maintenance Cost | 2 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
PETER RODGERS | (805) 781-5712 | PRODGERS@SLOCOG.ORG |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-99313 |
$1,000 | $-1,000 | $0 | ||||
Non-bond Funding | |||||||
State/Federal* |
$4,100 | $-4,100 | $0 | ||||
Local** |
$7,695 | $-7,695 | $0 | ||||
Total**** | $12,795 | $-12,795 | $0 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$195 | $-195 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$500 | $-500 | $0 | $0 | $0 | $0 | |
Right of Way |
$5,000 | $-5,000 | $0 | $0 | $0 | $0 | |
Construction |
$7,100 | $-7,100 | $0 | $0 | $0 | $0 | |
Total* | $12,795 | $-12,795 | $0 | $0 | $0 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/01/2017 06/01/2017 |
|
01/01/2017 06/01/2017 |
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/01/2017 04/01/2018 |
|
09/01/2017 04/01/2018 |
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
12/01/2016 03/01/2017 |
03/09/2018 |
12/01/2016 09/01/2018 |
5 | |
0 0 |
Begin Construction Phase
End Construction Phase |
05/01/2018 06/01/2019 |
03/09/2018 03/09/2018 |
01/01/2020 02/01/2021 |
0 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
07/01/2019 01/01/2020 |
03/09/2018 03/09/2018 |
03/01/2021 09/01/2021 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 5 | |
Reduced Operating/Maintenance Cost | 2 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31