Hand held radios and flexi glass at Depot

Description: Handheld radios will provide the transit evacuation team with a back up source of communications. And install polycarbonate bullet proof flexi glass at the transit depot

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kings
City Corcoran
Zip Code 93212
 
Senate District
16
Assembly District 30
Congressional District 30
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      2  
Reduced Operating/Maintenance Cost  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
KEVIN TROMBORG (559) 992-2151 X232   KEVIN.TROMBORG@CITYOFCORCORAN.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$27 $0 $27
Non-bond Funding
 
Total**** $27 $0 $27

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$27 $0 $27 $17 $17 $10
 
Total* $27 $0 $27 $17 $17 $10

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2017 

07/30/2020 
08/07/2018 

08/07/2018 
10/01/2017 

07/30/2020 
100   

 


Begin Closeout Phase

End Closeout Phase
10/01/2017 

07/30/2020 
08/07/2018 

08/07/2018 
10/01/2017 

01/09/2020 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 2
Reduced Operating/Maintenance Cost 5

Bond Funding Cost
Adopted:
$27,282
Current Approved:
$16,859
Actual Expenditures:
$16,859

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31