Bus Wash/Vault Facility Upgrades |
Description: Support bus operations at Fresno Area Express by upgrading day-to-day bus operations. Allocation will expand bus wash and vault relocation.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Fresno |
City | Fresno |
Zip Code | 93706 |
Senate District |
13 |
Assembly District | 31 |
Congressional District | 16 |
Caltrans District |
06 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Operating/Maintenance Cost | 10 | 10 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
DARLENE CHRISTAINSEN | (559) 621-1469 | DARLENE.CHRISTAINSEN@FRESNO.GOV |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $224 | $224 | ||||
PTMISEA-99313 |
$1,100 | $0 | $1,100 | ||||
PTMISEA-99314 |
$0 | $438 | $438 | ||||
Non-bond Funding | |||||||
Total**** | $1,100 | $662 | $1,762 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,100 | $662 | $1,762 | $1,762 | $1,762 | $0 | |
Total* | $1,100 | $662 | $1,762 | $1,762 | $1,762 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
05/31/2020 06/30/2020 |
02/14/2022 02/14/2022 |
02/28/2022 01/31/2023 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
05/31/2020 06/30/2020 |
02/14/2022 02/14/2022 |
03/31/2023 06/30/2023 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Operating/Maintenance Cost | 10 | 10 |
Bond Funding Cost | |
---|---|
Adopted: |
$1,100,000 |
Current Approved: |
$1,538,157 |
Actual Expenditures: |
$1,538,157 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31