Replace Vehicles - Fixed Route & Paratransit

Description: Purchase replacement vehicles for both fixed and paratransit fleets.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno
City Fresno
Zip Code 93706
 
Senate District
14
Assembly District 31
Congressional District 16
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      1  
Reduced Operating/Maintenance Cost  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DARLENE CHRISTAINSEN (559) 621-1469   DARLENE.CHRISTAINSEN@FRENSO.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $198 $198
PTMISEA-99313
$2,925 $0 $2,925
PTMISEA-99314
$27 $0 $27
Non-bond Funding
 
Total**** $2,952 $198 $3,151

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,952 $198 $3,151 $3,151 $3,151 $0
 
Total* $2,952 $198 $3,151 $3,151 $3,151 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/30/2020 

04/30/2020 
08/07/2023 

02/15/2023 
10/01/2019 

01/31/2023 
100   

 


Begin Closeout Phase

End Closeout Phase
04/01/2020 

04/30/2020 
08/07/2023 

02/15/2023 
02/01/2023 

03/31/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 1
Reduced Operating/Maintenance Cost 5

Bond Funding Cost
Adopted:
$2,952,114
Current Approved:
$2,952,114
Actual Expenditures:
$2,952,114

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31