Caltrans Logo

Transit Hub Right of Way Acquisition

Description: Project is the preparation of a right of way acquisition for the construction of the Lake Transit Hub to be located at the intersection of Dam Road Extension and South Center Dr.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Lake
City Ukiah
Zip Code 95482
 
Senate District
02
Assembly District 04
Congressional District 03
 
Caltrans District
01
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  10    10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JAMES SOOKNE (707) 234-3314   JSOOKNE@DBCTEAM.NET
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$189 $0 $189
PTMISEA-99314
$11 $0 $11
Non-bond Funding
 
Total**** $200 $0 $200

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$200 $0 $200 $200 $200 $0
 
Total* $200 $0 $200 $200 $200 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2018 

09/30/2019 
 

 
07/01/2018 

09/30/2019 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
09/08/2021 

09/08/2021 
04/01/2020 

03/31/2021 
100   

 


Begin Construction Phase

End Construction Phase
 

 
 

 
 

 
 

 


Begin Closeout Phase

End Closeout Phase
10/01/2019 

10/31/2019 
09/08/2021 

09/08/2021 
09/01/2021 

09/30/2021 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 10 10

Bond Funding Cost
Adopted:
$200,000
Current Approved:
$200,000
Actual Expenditures:
$200,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31