Caltrans Logo

Heavy Bus Lift Purchase

Description: The heavy bus lift in the Maint Facility has exceeded its useful life. The new lift will allow staff to complete repairs in a more timely manner, improving turnaround time and overall productivity.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Commerce
Zip Code 90040
 
Senate District
32
Assembly District 58
Congressional District 40
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10    52  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
CLAUDE MCFERGUSON (310) 887-4419   DIRECTOR-TRANSPORTATION@CI.COMMERCE.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99314
$52 $0 $52
Non-bond Funding
State/Federal*
$0 $56 $56
 
Total**** $52 $56 $107

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$52 $56 $107 $107 $107 $0
 
Total* $52 $56 $107 $107 $107 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
11/01/2017 

12/31/2017 
 

 
11/01/2017 

12/31/2017 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/01/2010 

 
 

 
11/01/2010 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
02/01/2018 

06/30/2018 
 

 
05/01/2017 

05/12/2017 
 

 


Begin Closeout Phase

End Closeout Phase
07/01/2018 

09/30/2018 
 

 
09/01/2018 

09/30/2018 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10 52

Bond Funding Cost
Adopted:
$51,544
Current Approved:
$51,544
Actual Expenditures:
$51,544

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31