Purchase up to 18 40ft CNG buses

Description: Purchase up to 18 40ft CNG buses in support of GTrans' fleet replacement plan over the next five years. Three buses will be for expanded service. Update - Purchased 9 buses.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Gardena
Zip Code 90249
 
Senate District
35
Assembly District 66
Congressional District 43
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  30      
Reduced Emissions  37      
Reduced Operating/Maintenance Cost  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ERNIE CRESPO (310) 965-8801   ECRESPO@CI.GARDENA.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $52 $52
PTMISEA-99314
$1,036 $369 $1,406
Non-bond Funding
State/Federal*
$0 $10,201 $10,201
Local**
$12,441 $-10,769 $1,672
 
Total**** $13,477 $-146 $13,331

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$13,477 $-146 $13,331 $13,331 $13,331 $0
 
Total* $13,477 $-146 $13,331 $13,331 $13,331 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2018 

03/30/2020 
10/02/2019 

 
01/01/2020 

06/30/2020 
100   

 


Begin Closeout Phase

End Closeout Phase
05/01/2020 

06/30/2020 
10/02/2019 

03/11/2021 
09/30/2020 

03/31/2021 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 30
Reduced Emissions 37
Reduced Operating/Maintenance Cost 10

Bond Funding Cost
Adopted:
$1,036,286
Current Approved:
$1,405,570
Actual Expenditures:
$1,405,570

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31