Real Time Passenger Information System

Description: Purchase and install Real Time Passenger Information System for the fixed-route transit vehicles in the Beach Cities Transit fleet.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Redondo Beach
Zip Code 90277
 
Senate District
26
Assembly District 66
Congressional District 33
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  2    1  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JOYCE ROONEY (310) 318-0610   JOYCE.ROONEY@REDONDO.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $15 $15
PTMISEA-99314
$93 $0 $93
Non-bond Funding
Local**
$0 $160 $160
 
Total**** $93 $175 $268

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$93 $175 $268 $109 $109 $160
 
Total* $93 $175 $268 $109 $109 $160

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/30/2017 

03/30/2018 
06/29/2020 

06/29/2020 
03/30/2019 

06/30/2019 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/01/2018 

05/30/2018 
04/19/2023 

04/19/2023 
12/30/2022 

03/30/2023 
100   

 


Begin Closeout Phase

End Closeout Phase
12/30/2018 

03/30/2019 
04/19/2023 

04/19/2023 
05/30/2023 

12/30/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 2 1

Bond Funding Cost
Adopted:
$93,346
Current Approved:
$93,346
Actual Expenditures:
$93,346

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31