Purchase Two CNG Buses

Description: Purchase two CNG buses to replace diesel powered buses.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Torrance
Zip Code 90503
 
Senate District
26
Assembly District 66
Congressional District 33, 43
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10      
Increased Ridership  15      
Reduced Emissions  20      
Reduced Operating/Maintenance Cost  10      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JAMES LEE (310) 781-6924   JAMESLEE@TORRANCECA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $117 $117
PTMISEA-99313
$0 $0 $0
PTMISEA-99314
$1,559 $-484 $1,076
Non-bond Funding
 
Total**** $1,559 $-367 $1,192

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,559 $-367 $1,192 $1,192 $1,192 $0
 
Total* $1,559 $-367 $1,192 $1,192 $1,192 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2018 

06/30/2018 
04/26/2022 

12/08/2023 
11/16/2021 

11/30/2024 
80   

 


Begin Closeout Phase

End Closeout Phase
12/30/2018 

 
12/08/2023 

12/08/2023 
12/01/2024 

12/31/2024 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10
Increased Ridership 15
Reduced Emissions 20
Reduced Operating/Maintenance Cost 10

Bond Funding Cost
Adopted:
$1,559,446
Current Approved:
$1,075,776
Actual Expenditures:
$1,075,776

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31