Caltrans Logo

TART Bus Purchase 2018

Description: Purchase (1) one 40-ft CNG transit coach bus at Tahoe Truckee Area Regional Transit (TART), to replace a 2014 CNG transit coach past its useful life.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Placer
City Auburn
Zip Code 95603
 
Senate District
04
Assembly District 01
Congressional District 04
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10    10  
Increased Ridership      3  
Reduced Emissions  94      
Reduced Operating/Maintenance Cost  15      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
WILL GARNER (530) 745-7582   WGARNER@PLACER.CA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $36 $36
PTMISEA-99313
$135 $7 $142
Non-bond Funding
State/Federal*
$331 $10 $341
Local**
$68 $-44 $25
 
Total**** $534 $9 $543

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$534 $9 $543 $543 $543 $0
 
Total* $534 $9 $543 $543 $543 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/31/2018 

03/01/2019 
 

 
01/31/2018 

03/01/2019 
100   

 


Begin Closeout Phase

End Closeout Phase
03/01/2019 

06/30/2019 
04/25/2019 

04/25/2019 
11/01/2019 

12/31/2020 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10 10
Increased Ridership 3
Reduced Emissions 94
Reduced Operating/Maintenance Cost 15

Bond Funding Cost
Adopted:
$134,714
Current Approved:
$141,508
Actual Expenditures:
$141,508

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31