Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
RTA Transit Coach Replacement Local Match |
Description: Replace three transit coaches with 40' low floor clean diesel coaches
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Luis Obispo |
City | San Luis Obsipo |
Zip Code | 93401 |
Senate District |
33 |
Assembly District | 15 |
Congressional District | 23 |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 5 | 5 |
Reduced Operating/Maintenance Cost | 5 | 5 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
GEOFF STRAW | (805) 781-4465 | GSTRAW@SLORTA.ORG |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-99313 |
$352 | $-33 | $320 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,188 | $72 | $1,260 | ||||
Total**** | $1,540 | $40 | $1,580 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$1,540 | $40 | $1,580 | $1,580 | $1,580 | $0 | |
Total* | $1,540 | $40 | $1,580 | $1,580 | $1,580 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
11/15/2017 06/30/2019 |
03/11/2020 03/11/2020 |
05/01/2018 05/01/2019 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
06/30/2019 |
03/11/2020 03/11/2020 |
06/01/2019 12/01/2019 |
100 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 5 | 5 |
Reduced Operating/Maintenance Cost | 5 | 5 |
Bond Funding Cost | |
---|---|
Adopted: |
$352,446 |
Current Approved: |
$319,791 |
Actual Expenditures: |
$319,791 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31