Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
RTA Bus Maintenance Facility Local Match |
Description: Construct a new RTA Bus Maintenance Facility on 6.5 acre site to meet long-term needs. The new facility will house operations, maintenance and administration in one building.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Luis Obispo |
City | San Luis Obsipo |
Zip Code | 93401 |
Senate District |
33 |
Assembly District | 15 |
Congressional District | 23 |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 5 | 5 |
Reduced Operating/Maintenance Cost | 5 | 5 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
GEOFF STRAW | (805) 781-4465 | GSTRAW@SLORTA.ORG |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $122 | $122 | ||||
PTMISEA-99313 |
$1,200 | $1,033 | $2,233 | ||||
PTMISEA-99314 |
$0 | $20 | $20 | ||||
Non-bond Funding | |||||||
State/Federal* |
$11,200 | $9,878 | $21,078 | ||||
Local** |
$0 | $1,742 | $1,742 | ||||
Total**** | $12,400 | $12,794 | $25,194 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$12,400 | $12,794 | $25,194 | $23,220 | $23,220 | $1,974 | |
Total* | $12,400 | $12,794 | $25,194 | $23,220 | $23,220 | $1,974 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/01/2018 08/31/2018 |
10/04/2019 10/04/2019 |
04/01/2018 12/30/2019 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
01/04/2019 11/01/2021 |
08/03/2022 03/02/2020 |
09/01/2020 06/30/2022 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
02/01/2022 06/30/2022 |
03/22/2021 02/14/2023 |
06/30/2022 06/30/2023 |
100 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 5 | 5 |
Reduced Operating/Maintenance Cost | 5 | 5 |
Bond Funding Cost | |
---|---|
Adopted: |
$1,200,000 |
Current Approved: |
$2,252,491 |
Actual Expenditures: |
$2,252,491 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31