Description: Develop the design plans, specifications and estimated activities for the future construction of the Transit Maintenance Facility, servicing the transit needs to the local and regional community.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Trinity |
City | Weaverville |
Zip Code | 96093 |
Senate District |
02 |
Assembly District | 02 |
Congressional District | 02 |
Caltrans District |
02 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 15 | 20 |
Increased Ridership | 10 | |
Reduced Emissions | 10 | |
Reduced Operating/Maintenance Cost | 10 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
POLLY CHAPMAN | (530) 623-1365 X3427 | PCHAPMAN@TRINITYCOUNTY.ORG |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $10 | $10 | ||||
PTMISEA-99313 |
$152 | $19 | $171 | ||||
PTMISEA-99314 |
$3 | $0 | $3 | ||||
Non-bond Funding | |||||||
Local** |
$0 | $299 | $299 | ||||
Total**** | $155 | $328 | $483 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$155 | $19 | $174 | $174 | $174 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$0 | $309 | $309 | $309 | $309 | $0 | |
Total* | $155 | $328 | $483 | $483 | $483 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
12/01/2017 12/01/2018 |
|
12/01/2017 12/01/2018 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
02/01/2019 08/01/2020 |
08/18/2023 08/18/2023 |
09/01/2022 03/31/2023 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
10/01/2020 09/01/2021 |
08/18/2023 08/18/2023 |
05/01/2023 06/30/2023 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
10/01/2021 12/01/2021 |
08/18/2023 08/18/2023 |
06/30/2023 08/17/2023 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 15 | 20 |
Increased Ridership | 10 | |
Reduced Emissions | 10 | |
Reduced Operating/Maintenance Cost | 10 |
Bond Funding Cost | |
---|---|
Adopted: |
$155,398 |
Current Approved: |
$173,924 |
Actual Expenditures: |
$173,924 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31