Caltrans Logo

San Gabriel Valley Grade Separation Program

Description: Alameda Corridor East, Grade Separation, Rail-Highway

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Alhambra, Industry, Pico Rivera, Pomona, Rosemead, San Gabriel
Zip Code
 
Senate District
21
Assembly District 49
Congressional District 29
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Rail/Highway At-Grade Crossings Eliminated  4    4  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
ACE Construction Authority Mark Christoffels (626) 962-9292   mchristoffels@theaceproject.org
Design (PS&E) Phase
ACE Construction Authority Mark Christoffels (626) 962-9292   mchristoffels@theaceproject.org
Right of Way Phase
ACE Construction Authority Mark Christoffels (626) 962-9292   mchristoffels@theaceproject.org
Construction Phase
ACE Construction Authority Mark Christoffels (626) 962-9292   mchristoffels@theaceproject.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$336,600 $-98,822 $237,778
Non-bond Funding
State/Federal*
$133,500 $-128,500 $5,000
Local**
$253,466 $71,317 $324,783
Private***
$0 $27,949 $27,949
 
Total**** $723,566 $-128,056 $595,510

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$34,100 $13,972 $48,072 $46,214 $46,214 $1,858
Right of Way
$21,770 $58,405 $80,175 $58,185 $58,185 $21,990
Construction
$667,696 $-200,433 $467,263 $350,367 $345,974 $121,289
 
Total* $723,566 $-128,056 $595,510 $454,767 $450,373 $145,137

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2003 

12/01/2009 
 

06/23/2011 
07/01/2003 

11/04/2010 
100  07/01/2003 

11/04/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2009 

12/01/2010 
 

06/27/2012 
06/01/2009 

02/01/2012 
100  06/01/2009 

02/27/2012 


-1 
Begin Right of Way Phase

End Right of Way Phase
12/01/2009 

11/01/2010 
06/27/2012 

06/23/2011 
12/01/2010 

06/01/2011 
100  11/04/2010 

06/21/2011 


-1 
Begin Construction Phase

End Construction Phase
04/01/2011 

07/01/2014 
06/23/2011 

08/06/2013 
06/30/2004 

09/30/2017 
100  08/24/2011 

08/27/2018 
-87 

-11 
Begin Closeout Phase

End Closeout Phase
12/01/2014 

03/01/2016 
08/06/2013 

 
01/31/2010 

11/30/2018 
100  01/15/2019 

12/31/2019 
-109 

-13 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Rail/Highway At-Grade Crossings Eliminated 4 4

Bond Funding Cost
Adopted:
$336,600,000
Current Approved:
$222,618,000
Actual Expenditures:
$216,358,000

 

Status as of December 31, 2023.